Home» On Going Project»Station improvement and development work at Lohta, Vyas Nagar, Shivpur and Babatpur station under Amrit Bharat Station Scheme in Lucknow Division of Northern Railway.

Station improvement and development work at Lohta, Vyas Nagar, Shivpur and Babatpur station under Amrit Bharat Station Scheme in Lucknow Division of Northern Railway.

February 18, 2020   to     February 18, 2020

Description of Work

Station improvement and development work at Lohta, Vyas Nagar, Shivpur and Babatpur Station under Amrit Bharat Station Scheme in Lucknow Division of Northern Railway

Participation %

Partner Name

% of Partner

% of DC

 

 

100

Contract No. & Date:

Letter No: LUCKNOW-NR-DIVISION-ENGINEERING/14SrDEN-III-LKO-2023-24/ 00952690089742 dated 25.10.2023

Name & address of Employer, Tel./Fax./Email

Northern Railway

Stipulated Period of completion in Months

12

Date of Start

10/25/2023

Anticipated Date of Completion

10/25/2024

Scheduled Date of Completion

12/18/2025

Contract Amount (in Cr.)

₹ 33.6003559

Revised Contract Amount (in Cr.)

 

Value of Work Completed (in Cr.)

 

Value of Balance work (in Cr.)

 

Work Completion (%)

 

Balance work (%)

 

EOT Details if any

EOT 1

EOT 2

EOT 3

EOT 4

EOT 5

EOT 6

12/18/2025