Description of Work |
Construction of Station - cum - S&T building, gate lodges, PF sheds, Foot Over bridges, Passenger Platforms, Station approach roads, Level crossing roads, Supply and fixing of lifting barriers, yard drain, circulating area, Construction and fixing of various sectional boards and other allied and misc. works between Sagauli (including) to Bettiah (including) in connection with SGL-NKE doubling project under Dy. CE/Con/BTH in Samastipur Division | ||||||||||||
Participation % |
|
||||||||||||
Contract No. & Date: |
No. ECR/CAO/Con/North/ETN-88 -19-20 Dated 18-02-2020 | ||||||||||||
Name & address of Employer, Tel./Fax./Email |
East Central Railway | ||||||||||||
Stipulated Period of completion in Months |
|||||||||||||
Date of Start |
2/18/2020 | ||||||||||||
Anticipated Date of Completion |
7/18/2022 | ||||||||||||
Scheduled Date of Completion |
3/30/2025 | ||||||||||||
Contract Amount (in Cr.) |
₹ 32,15 | ||||||||||||
Revised Contract Amount (in Cr.) |
|||||||||||||
Value of Work Completed (in Cr.) |
|||||||||||||
Value of Balance work (in Cr.) |
|||||||||||||
Work Completion (%) |
|||||||||||||
Balance work (%) |
|||||||||||||
EOT Details if any |
|