Description of Work |
Construction of Forensic Lab Gonda | ||||||||||||
|
Participation % |
|
||||||||||||
|
Contract No. & Date: |
916/GM(EZ-I)/AyodhyaUnit/R.N.N/23 | ||||||||||||
|
Name & address of Employer, Tel./Fax./Email |
Uttar Pradesh Rajkiya Nirman Nigam Limited | ||||||||||||
|
Stipulated Period of completion in Months |
12 | ||||||||||||
|
Date of Start |
11/21/2023 | ||||||||||||
|
Anticipated Date of Completion |
11/21/2024 | ||||||||||||
|
Scheduled Date of Completion |
7/30/2025 | ||||||||||||
|
Contract Amount (in Cr.) |
₹12.55 | ||||||||||||
|
Revised Contract Amount (in Cr.) |
|||||||||||||
|
Value of Work Completed (in Cr.) |
|||||||||||||
|
Value of Balance work (in Cr.) |
|||||||||||||
|
Work Completion (%) |
|||||||||||||
|
Balance work (%) |
|||||||||||||
|
EOT Details if any |
|