Name of Work |
Construction of Bhajan Sandhya Sthal, Ayodhya Faizabad (U.P.) |
Year of Completion |
2020 |
Date of Completion |
3/25/2020 |
Financial Year |
2019-2020 |
Location |
Uttar Pradesh |
Agreement / Work Order No. |
C-06/G.M.:(Fzd Zone)/NIVIDA/RNN/17 dated 17.03.2017 |
Mode of Work |
Item Rate |
Type of Work |
Building |
Client Name |
Uttar Pradesh Rajya Nirman Nigam Ltd. |
Estimated Cost (in Cr.) |
₹ 114,947,625.00 |
Revised Estimated Cost (in Cr.) |
₹ 190,236,000.00 |
Completion Cost (in Cr.) |
₹ 179,424,000.00 |