Description of Work |
Construction of RCC boundary wall for raising of speed from 130 Kmph to 160 Kmph in Tundla - Ghaziabad section under Sr.DEN/5/Prayagraj | ||||||||||||
|
Participation % |
|
||||||||||||
|
Contract No. & Date: |
IN-DL75828097471482U dated 12/01/2022 | ||||||||||||
|
Name & address of Employer, Tel./Fax./Email |
S and P Infrastructure Developers Pvt. Ltd. - New Delhi | ||||||||||||
|
Stipulated Period of completion in Months |
21.6 | ||||||||||||
|
Date of Start |
1/12/2022 | ||||||||||||
|
Anticipated Date of Completion |
10/12/2023 | ||||||||||||
|
Scheduled Date of Completion |
|||||||||||||
|
Contract Amount (in Cr.) |
₹ 62.7 | ||||||||||||
|
Revised Contract Amount (in Cr.) |
₹ 90 | ||||||||||||
|
Value of Work Completed (in Cr.) |
|||||||||||||
|
Value of Balance work (in Cr.) |
|||||||||||||
|
Work Completion (%) |
|||||||||||||
|
Balance work (%) |
|||||||||||||
|
EOT Details if any |
|